Greetings,
We're happy to report that Northstar Commuter Rail remains on
track and is preparing to begin construction this summer. Today,
the Northstar Corridor Development Authority (NCDA) Executive
Committee approved the first of five payments to BNSF Railway
for easements that will give Northstar access to BNSF train
tracks.
The $24 million payment will be combined with $10 million in
earnest money paid early this spring to make up the first
payment to BNSF, due May 31. For a total of $107.5 million, the
state will receive permanent easements from BNSF, which will
allow Northstar to use BNSF tracks between Big Lake and downtown
Minneapolis for the entire life of the commuter rail system.
May 31 is also the execution date of all current Northstar
agreements with BNSF. Click here to read the full news release.
Today's decision follows another exciting breakthrough last
week: the Federal Transit Administration (FTA) invited the NCDA
to formally apply for the 50 percent federal funding match.
According to the FTA, Northstar's recent progress gives the FTA
the "necessary confidence that this project is a viable
candidate" for a Full Funding Grant Agreement. Click here to read more.
This reassures us that Northstar is well-positioned to
receive federal funding this year and open for service in late
2009. It's also a great acknowledgement of our efforts to
advance commuter rail transit as a highly efficient way to move
Minnesotans through one of the state's most rapidly growing
corridors.
Sincerely,
Dan Erhart NCDA Chair
|